Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#179118

Postby Proselenes » November 9th, 2018, 9:19 am

Image

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#181192

Postby Proselenes » November 18th, 2018, 7:32 am

Weather has been excellent really.

https://www.accuweather.com/en/mn/bayan ... =11/1/2018


This coming week they should enter the Main Target Zone, if not already. Fingers crossed something good happens, but as always, be prepared for the duster, its the most likely outcome.

.

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#182954

Postby Proselenes » November 26th, 2018, 8:53 am

Wild Horse-1 is a duster as per todays RNS.

Got to wait for the drills in 2019 now (all of which are fully funded based on the current plans for 4 drills.


If you take the content of the RNS it looks like :

Next up will be the three low cost Block XX drills. These are all in effect appraisal and have very high chance of success. Each and every one of them is worth more than the current share price.

Drill these three first seems to be the plan, then I think a fund raising at a much higher price.

Fund raising will be for drilling in Block V where they now have (based on the SL-1 drill and latest seismic) three very large 4 way dip prospects. The fund raising will therefore pave the way for a 2 or 3 well drill campaign in Block 5. This is when the rig will drill Fox-1 and then one or two other new prospects they are working on.

So thats how I see it panning out.

1st Drill Block XX (already funded - no need for fund raise)
2nd Drill Block XX (already funded - no need for fund raise)
Fund raising based on success in Block XX and new leads.
3rd Drill Block XX (already funded - no need for fund raise)
1st Drill Block V (Fox-1) (already funded - no need for fund raise)
2nd Drill Block V (new prospect in the south of the license) Fund raise required.
3rd Drill Block V (new prospect in the south of the license) Fund raise required.

dspp
Lemon Half
Posts: 5884
Joined: November 4th, 2016, 10:53 am
Has thanked: 5825 times
Been thanked: 2127 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#182969

Postby dspp » November 26th, 2018, 9:53 am

Thank you Prosolenes. Just goes to show how risk small exploration companies are, even in the most benign of locations.

Full RNs available here is worth reading imho : https://www.proactiveinvestors.co.uk/LO ... 7_13879407

Fortunately I had only cookie jar quantities in this, not beer money quantities. That's because when HUR went to 40p I switched some across :)

regards, dspp

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#183138

Postby Proselenes » November 27th, 2018, 5:07 am

I purchased another chunk of HUR yesterday as the price was 40p.

Got another load of JOG too as that was below 180p again.

Both bargain prices.

dspp
Lemon Half
Posts: 5884
Joined: November 4th, 2016, 10:53 am
Has thanked: 5825 times
Been thanked: 2127 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#192353

Postby dspp » January 10th, 2019, 11:42 am

RNS ops update out today
http://irpages2.equitystory.com/website ... e=28487347

and 2019 investor presentation
https://www.petromatadgroup.com/wp-cont ... -Matad.pdf

(personally when HUR went down to 40p I sold my small MATD and added extra HUR)

- dspp

dspp
Lemon Half
Posts: 5884
Joined: November 4th, 2016, 10:53 am
Has thanked: 5825 times
Been thanked: 2127 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#206188

Postby dspp » March 7th, 2019, 11:35 am

RNS ops update out today

http://irpages2.equitystory.com/website ... e=28727022

Highlights

- 2019 four well drilling campaign: Heron, Gazelle, Red Deer (all Block XX) and a further exploration well in Block V, or appraisal of a Block XX discovery

- Heron

o Heron 1 well planned as first well of 2019 campaign, with spudding targeted for Q2 2019

o More than 50% resource uplift at Heron Prospect to 25 MMbo from 16 MMbo following mapping of reprocessed 2D seismic

o Analysis indicates the Heron Prospect is the southerly extension of a proven oil-bearing structure drilled in Petro China's adjacent Block XIX

- Gazelle high-graded to second Block XX well as new mapping shows it to be directly up dip of a Petro China discovery well on the same migration path

- Red Deer Prospect location remains unchanged, targeting 48 MMbo of mean prospective recoverable resource

- Heron, Gazelle and Red Deer environmental permits for drilling approved and CSR teams mobilised to well sites

- Regulatory approval received for two-rig strategy for limited additional cost to allow for simultaneous drilling of prospects - negotiations with rig contractors nearing finalisation

- Applications for Block IV and V PSCs being prepared for two-year extensions, with submission expected shortly

- Ongoing analysis of Snow Leopard 1 well, Block V, has significantly enhanced the prospectivity of the Block and in particular the Raptor trend



etc ...... dspp

(personally I remain out of this, but it is an interesting one to watch)

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#223552

Postby Proselenes » May 22nd, 2019, 4:33 am

2019 Drilling :

1/ Heron-1 due to spud early to mid July 2019 - 30 to 40 days to drill - Block 20
2/ Gazelle-1 due to spud late August 2019 - 25 to 35 days to drill - Block 20
3/ Red Deer 1 due to spud mid to late July 2019 - 25 to 35 days to drill- Block 20

4th well - To Be Decided Either in Block 5 (Raptors) or another in Block 20

.

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#225099

Postby Proselenes » May 28th, 2019, 11:02 pm

Petro Matad @Petro_Matad

Site construction is underway at #Heron1 and is expected to be completed within 10 days #MATD

Image

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#225929

Postby Proselenes » June 1st, 2019, 8:18 am

I believe Heron COS is 75% and Red Deer COS was over 40%.

Red Deer is a basin opening play, if that comes in thats worth a load plus a lot more.

Heron 25 MMBO circa 18p a share
Red Deer-1 48 MMBO circa 32p a share (plus loads of follow on leads)
Gazelle 13 MMBO circa 8.5p a share

Drill 4.......depending on where it is, if Block V then its a biggie, 200p a share potential, if its Block XX again then maybe another 20p to 30p a share size drill.

Both Heron and Red Deer one due to be at TD at the same time, mid August.

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#227756

Postby Proselenes » June 7th, 2019, 1:00 pm

Image

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#228802

Postby Proselenes » June 11th, 2019, 10:24 pm

Image


dspp
Lemon Half
Posts: 5884
Joined: November 4th, 2016, 10:53 am
Has thanked: 5825 times
Been thanked: 2127 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#232163

Postby dspp » June 26th, 2019, 1:42 pm

The key bits in the RNS are :

· The Company is on track to spud the Heron 1 during July 2019, using DQE's rig 40105. The Gazelle 1 well will follow immediately after Heron 1 operations, allowing for a short rig move

· Red Deer 1 is expected to spud before the end of July 2019, using Daton's rig DXZ1


- dspp

Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#232567

Postby Proselenes » June 28th, 2019, 2:51 pm


Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#233654

Postby Proselenes » July 3rd, 2019, 12:30 pm


Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#233883

Postby Proselenes » July 4th, 2019, 10:50 am

Image


Proselenes
Lemon Quarter
Posts: 1372
Joined: November 15th, 2016, 6:04 am
Has thanked: 58 times
Been thanked: 389 times

Re: Petro Matad - Fully funded 6 well campaign for H2 2018/H1 2019

#235777

Postby Proselenes » July 11th, 2019, 9:07 am

Image